South Lamar Boulevard Corridor Project

South Lamar Boulevard Corridor Project

Mobility, safety and connectivity improvements are coming to South Lamar Boulevard from Riverside Drive to Ben White Boulevard. The improvements are funded by the 2016 Austin Mobility Bond.

About the Project

Austin Corridor Mobility Program

Status: Under Construction

August 27, 2026, Status Update: The City of Austin continues making progress on multiple projects along South Lamar Boulevard. Below is the latest schedule and what to expect next.

 

South Lamar Corridor Improvements (Full Corridor)

Status: Pre-Construction

The overall South Lamar Corridor project is approaching final design. To help deliver improvements more efficiently, the City is dividing the corridor into two segments at Montclaire Street:

  • Southern Segment (Montclaire Street to US-290):
    Bid solicitations began in July 2026; construction is anticipated to start in late 2026.
     
  • Northern Segment (Barton Springs Road to Montclaire Street):
    Expected to be sent to bid later, closer to 2029, as the southern segment nears completion.

 

Mary Street Roundabout

Status: Complete

Work on the Mary Street roundabout was completed in spring 2026. See photos of the completed roundabout.

The new roundabout:

  • Improves safety and traffic flow at the intersection
  • Adds pedestrian crossings at each leg of the roundabout
  • Includes shared-use paths for people walking and biking

 

Stormwater Improvements

Status: Under Construction

Construction is underway on the storm drain project, which will improve drainage and support long-term roadway conditions along the corridor. This work is expected to continue through the next several years, with completion anticipated in 2027.

 

Del Curto / Bluebonnet Roundabout

Status: Pre-Construction

The City has selected a contractor for the Del Curto/Bluebonnet roundabout (the same contractor currently working on the storm drain project). Construction is expected to begin in Fall 2026.

     

    Treadwell Connection Update

    Status: Removed from Project Scope

    As part of preliminary engineering, the City requested approval from Union Pacific Railroad to connect Treadwell Street to South Lamar via either an overpass or underpass. Union Pacific denied both requests, so this connection has been removed from the current project scope.

    While it is not included in the corridor program due to feasibility and funding constraints, it could be considered in the future if prioritized through local mobility programs.

    Project Timeline

    complete
    complete

    Preliminary Engineering Report

    Completed April 2016

    complete
    complete

    NEPA Public Hearing

    National Environmental Policy Act (NEPA) Virtual Public Hearing
    Riverside Drive to Barton Springs Road

    Conducted July 2020

    complete
    complete

    30% Design

    Completed August 2020

    complete
    complete

    60% Design

    Completed December 2020

    complete
    complete

    90% Design

    Completed March 2021

    complete
    complete

    Final Design

    Completed May 2026

    live
    live

    Solicit Bids

    Southern Segment (Montclaire Street to US-290)

    planned
    planned

    Under Construction

    Southern Segment (Montclaire Street to US-290)

    planned
    planned

    Solicit Bids

    Northern Segment (Barton Springs Road to Montclaire Street)

    planned
    planned

    Under Construction

    Northern Segment (Barton Springs Road to Montclaire Street)