Project description  

The Northeast Service Center (NESC) will be located at 8301 Johnny Morris Road. It will house ARR and AFMS under a modern, efficient campus designed to serve a growing city. The project includes:

  • Operations and administrative buildings to support ARR vehicles and City fleet units.
  • A community room available for neighborhood associations, civic groups and non-profits.
  • Landscaped plazas and flexible-use outdoor gathering area.
  • Public art installations through Art in Public Places.
  • Improved traffic flow and pedestrian safety, including turn lanes and a beacon crosswalk.

Buildings are designed to meet WELL Silver and Austin Energy Green Building Three-Star certifications, with rainwater collection, reclaimed water connections, expanded solar capacity and low-VOC materials.

This is the City of Austin’s first project developed through a public-private partnership using the Austin Public Facilities Corporation.

 

Community impact

ARR and AFMS are committed to minimizing neighborhood disruption during construction:

  • Noise and lighting: All work will comply with City ordinances.
  • Traffic flow: Construction vehicles will primarily enter from the north; turn lanes and traffic control measures will reduce neighborhood impact.
  • Operations: Once open, the facility will service collection trucks, street sweepers and single passenger fleet vehicles. These will operate mostly Monday through Friday, 5 a.m.to 7 p.m.

We welcome your questions and concerns throughout the project. Reach out to us at NESC@austintexas.gov and subscribe to digital updates. We are also sending regular mailers about construction progress to community members and will be adding additional ways to connect with the team to this page, as opportunities become available.

 

Funding and resources

City Council authorized funding in December 2024.

  • Project budget: $253.5 million
  • Funding sources; ARR (monthly rates) and AFMS (General Fund) 

 

Contacts  

Email NESC@austintexas.gov or call 3-1-1 (512-974-2000). 

complete
complete
September 2022 – September 2024

Planning & Zoning Phase

  • Zero Waste Advisory Commission briefings (Sept 2022, Apr 2024, Dec 2024)
  • Community meetings with Colony Park Neighborhood Association (May 20) and Turner-Roberts Recreation Center (June 12, Aug 22)
  • Zoning and Platting Commission approval (June 2024)
  • Council approvals for zoning (Sept 2024) and design funding (May 2024)

complete
complete
December 2024

Council approved project funding and authorized negotiations with development partner

complete
complete
January 2025

City planning review process began

live
live
March 2025

Procurement and permitting began

live
live
September 2025

Construction began

  • Mailers sent to community about construction and events
  • Sept. 16: In-person info table at Turner-Roberts Recreation Center
  • Sept. 17: Virtual open house via Zoom
  • Sept. 18: In-person info table at Overton Elementary Back-to-School Night
  • Sept. 23: Groundbreaking ceremony

planned
planned
Fall 2027

Estimated project completion