Waller Beach Duct Bank Upgrade
Waller Beach Duct Bank Upgrade
The Waller Beach Duct Bank Upgrade will route circuits from the Rainey Street substation underneath parkland along Lady Bird Lake between Brazos Street and Trinity Street to the downtown network. It is a critical infrastructure investment designed to strengthen long-term electrical reliability for downtown Austin and surrounding areas as demand continues to grow.
Latest Updates - November 2026
Upcoming Work
Crews have removed all tunneling equipment and are scheduled to install electrical conduits and grouting inside the tunnel.
Holiday Construction Schedule - Crews will pause field operations during the following periods:
Thanksgiving: Thursday, November 26, through Sunday, November 29, 2026. Work will resume on Monday, November 30.
Christmas and New Year: Friday, December 18, 2026, through Sunday, January 3, 2027. Work will resume on Monday, January 4.
Construction areas will remain closed and secured throughout both holiday shutdowns, even though no field operations will take place during these periods.
These planned breaks have been incorporated into the project schedule and are not expected to affect project milestones or the overall construction timeline.
Pedestrian Access
- The trail detour in front of the Boathouse will remain in place through summer 2027. Pedestrians and cyclists are urged to use caution in the area. Additional signage and a mirror have been installed to improve trail safety in this area.
View of the construction zone and staging areas on Brazos Street south of Cesar Chavez
For more information or to submit questions:
Carolyn Perez, Community Engagement Consultant Carolyn.perez@austinenergy.com
Frequently Asked Questions
The project is installing 1,000 feet of underground duct bank and new electrical manholes to route power from the Rainey Street substation into the downtown network.
As downtown Austin continues to grow, additional electrical capacity is needed to support new development and ensure reliable service.
This location was selected based on engineering requirements and the need to connect the Rainey Street substation to the existing downtown electrical network.
In July 2026, a portion of the trail was temporarily rerouted. This detour will be in place through summer 2027. Directional signage and a mirror have been installed to guide trail users and improve pedestrian and cyclist safety.
Construction is expected to begin in May 2026 and last approximately one year, with work occurring in phases.
Crews will follow traffic control plans that may cause increased traffic on Brazos Street during equipment mobilization. Street parking on Brazos south of Cesar Chavez will be unavailable during construction, but access to parking garages and nearby properties will be maintained.
City teams coordinate across departments to minimize overlap where possible, but some projects must occur at the same time due to scheduling, funding, and infrastructure needs.
The contractor will maintain access to businesses, residences, and surrounding destinations throughout construction.
The contractor will complete the work in phases, use traffic control measures, and apply construction methods such as micro-tunneling to reduce surface disruption and protect parkland and trees.
In general, work will take place Monday through Friday from 7 a.m. to 7 p.m. with occasional weekend work if approved by the City. A 24-7 work schedule will be in effect near the Brazos cul-de-sac from September 28 - October 14, 2026.