Skip Navigation

Waller Beach Duct Bank Upgrade

Waller Beach Duct Bank Upgrade

The Waller Beach Duct Bank Upgrade will route circuits from the Rainey Street substation underneath parkland along Lady Bird Lake between Brazos Street and Trinity Street to the downtown network. It is a critical infrastructure investment designed to strengthen long-term electrical reliability for downtown Austin and surrounding areas as demand continues to grow.

Step 1

Latest Updates - October 2026 

  • Tunneling Operations Complete

    • Crews have finished approximately 785 linear feet of tunneling and are now transitioning to equipment removal and site cleanup. 

  • Equipment Removal and Site Cleanup - upcoming activities

    • Mobilizing a crane on the Trinity Street side to remove the tunnel boring machine.

    • Removing heavy equipment from the Brazos Street side. Weekend work may occur as needed, with activities limited to 10 a.m. to 7 p.m. on Saturdays and Sundays to minimize disruptions to nearby hotels and properties. 

  • Upcoming Water Line Work

    • Planning is underway for the next phase of water line construction. The project team is evaluating ways to minimize potential service interruptions to nearby hotels and properties, including the possible use of temporary water connections.

    • A site visit will be scheduled to assess construction logistics and potential temporary connections. Additional details about the schedule and any anticipated service interruptions will be shared as planning progresses. 

  • Pedestrian Access
    • Installation of the temporary Phase 2 pedestrian walkway along Trinity Street has been delayed to allow for crane operations. The walkway will be installed once work is complete.
    • The trail detour in front of the Boathouse will remain in place through summer 2027. Pedestrians and cyclists are urged to use caution in the area. Additional signage and a mirror have been installed to improve trail safety in this area.

Aerial view that shows where the staging areas at the end of Brazos Street south of Cesar Chavez

View of the construction zone and staging areas on Brazos Street south of Cesar Chavez

For more information or to submit questions:               

Carolyn Perez, Community Engagement Consultant                                  Carolyn.perez@austinenergy.com

Frequently Asked Questions

The project is installing 1,000 feet of underground duct bank and new electrical manholes to route power from the Rainey Street substation into the downtown network.

As downtown Austin continues to grow, additional electrical capacity is needed to support new development and ensure reliable service. 

This location was selected based on engineering requirements and the need to connect the Rainey Street substation to the existing downtown electrical network.

In July 2026, a portion of the trail was temporarily rerouted. This detour will be in place through summer 2027. Directional signage and a mirror have been installed to guide trail users and improve pedestrian and cyclist safety. 

Construction is expected to begin in May 2026 and last approximately one year, with work occurring in phases.

Crews will follow traffic control plans that may cause increased traffic on Brazos Street during equipment mobilization. Street parking on Brazos south of Cesar Chavez will be unavailable during construction, but access to parking garages and nearby properties will be maintained.

 

City teams coordinate across departments to minimize overlap where possible, but some projects must occur at the same time due to scheduling, funding, and infrastructure needs.

The contractor will maintain access to businesses, residences, and surrounding destinations throughout construction.

The contractor will complete the work in phases, use traffic control measures, and apply construction methods such as micro-tunneling to reduce surface disruption and protect parkland and trees.

In general, work will take place Monday through Friday from 7 a.m. to 7 p.m. with occasional weekend work if approved by the City. A 24-7 work schedule will be in effect near the Brazos cul-de-sac from September 28 - October 14, 2026.