Airport Project

Share on Facebook Share on Twitter Share on Linkedin Email this link

English | Español


In 1999, Austin-Bergstrom International Airport (AUS), which is owned and operated by the City of Austin, opened its doors to Austin and Central Texas and has been growing ever since. 2019 was the airport’s busiest year, with over 17 million passengers flying out of AUS. As the airport continues to recover from the impacts of the COVID-19 pandemic, the demand for air travel has significantly increased and the expected number of flights and passengers will double in 20 years. With an increasing demand for air travel and development at the airport, the airport must construct a second Jet-A fuel, or airplane fuel, facility to have enough fuel supply in the coming years to support a growing airport, a growing city and a growing economy.


New Facility Project Updates

May 2022:

Crews installed erosion control measures and began excavation for stormwater systems and electrical ductbanks. Work started on the transfer line systems and grading for an airport internal perimeter road.


Grading for new airport perimeter road


Stormwater manhole installation

April 2022:

Following the Austin City Council meeting on April 7, 2022 and vote on Item 43, the Department of Aviation issued a Notice to Proceed to the airlines to begin construction of the new fuel facility.

Construction began on the new Jet-A fuel storage facility began with the installation of temporary construction site entrances, project signage, and a project site gate. Construction crews began the installation of the Stormwater Pollution Prevention Plan and located utilities. Construction trailers and portables have been delivered to the site and will be set-up in the coming weeks for site crews and project staff to work from.

Temporary construction entrance

Temporary construction entrance


Project Background, Environmental Assessment, Community Outreach and More

Current Airplane Fuel Facility - Background & History

The airport’s main airplane fuel facility storage was constructed in 1998 and is located next to the Barbara Jordan Terminal. The current facility consists of two fuel tanks, one holds 481,000 and the other 691,700 gallons. This facility was created to be the safest and most efficient way to store and supply airplane fuel. It is continuously monitored and undergoes regular inspections by the Austin Fire Department, the Department of Aviation and the airlines. The facility is owned by the airlines that serve AUS and is operated by an independent aviation fueling services provider. The new facility will also be owned and operated by the airlines and their fueling services provider, with the same 24/7 monitoring and regular safety inspections.

For more information about the new facility, read the project fact sheet.


The Need For A New Facility 

Since the airport first opened, the number of annual passengers has tripled and the current facility no longer meets the needs of Austin’s growing community. The facility currently has a 2–3-day fuel supply, which doesn't meet the 5-7 day industry standard and cannot support future air service growth for 2022 and beyond. AUS forecasts an increase in fuel demand by an average of 3% to 5% annually over the next ten years.

The new facility will provide a more reliable, safe supply of fuel for the airlines and reliable air service for our community. It was identified as a development project through the airport’s 2040 Master Plan process. 

Watch this informational video about how AUS's fuel facility operates:


The AUS 2040 Master Plan

In 2017, the Department of Aviation began creating the 2040 Master Plan, which guides the airport’s growth as it doubles in size and serves as a roadmap to the future modernization of AUS. The need for a new fuel facility and the location of the new fuel facility were identified through this process and are in the final 2040 Master Plan document, which was approved by the Austin City Council and the Federal Aviation Administration. 

Before an airplane fuel facility is constructed, an environmental review is done to evaluate the potential environmental impact of the facility. All information from the review is presented to the Federal Aviation Administration (FAA), the administration that determines if it is safe to create a facility in the first place. If no significant impacts to air quality, socioeconomics or environmental justice, water resources, or other surroundings are expected to occur, then it’s safe to build a fuel facility. In preparation for the new fuel facility, AUS, the airlines and a team of consultants conducted an environmental review and submitted their review to the FAA. The review was granted approval by the FAA on April 8, 2020.


AUS 2040 Master Plan Public Workshops

From 2017 - 2018, the Department of Aviation hosted a series of Master Plan Public Workshops, Project Advisory Committee and Technical Advisory Committee meetings. You can review the archived meeting materials at this webpage:

  • October 12, 2017 - Public Workshop #1
  • April 19, 2018 - Public Workshop #2
  • June 7, 2018 - Public Workshop #3
  • September 6, 2018 - Public Workshop #4
Information, including project locations, for all 61 Master Plan projects were presented to the community throughout these meetings.


District 2 Fall 2021 Community Meetings

In fall 2021, the Department of Aviation and a representative from the engineering firm who is designing the new facility shared a presentation and answered community members' questions. You can view the presentation at this link.

  • October 4 - Virtual Meeting
  • November 10 - In-Person Meeting

January 29, 2022 Community Information Meetings

On Saturday, January 29, the City of Austin Department of Aviation hosted three community information meetings to inform community members and connect them to educational resources about the site selection, operations, safety, and security features of a proposed jet fuel storage facility. The meetings were in response to City of Austin Council Resolution NO. 20211209-061 and were intended to address the digital divide and language access barriers experienced by community members. One virtual meeting and two limited attendance in-person meetings were held. Both meetings provided simultaneous Spanish interpretation by professional interpreters.

View the February 7, 2022 memo from the Department of Aviation to Mayor and City Council to learn more about how these meetings were attended and publicized.

March 7, 2022 Listening Session

On March 7, 2022 Department of Aviation leadership attended a listening session led by community members to hear personal testimony for airport-adjacent neighbors and community members who were affected by the historic injustice of the East Austin petroleum storage tanks.



April 5, 2022 Austin City Council Work Session - Jet Fuel Storage Facility

AUS leadership briefed Austin City Council on the Fuel Facility Project at the City Council Work Session on April 5, 2022. The Work Session was recorded by ATXN which can be watched online at: https://austintx.new.swagit.com/videos/158053


English | Español


In 1999, Austin-Bergstrom International Airport (AUS), which is owned and operated by the City of Austin, opened its doors to Austin and Central Texas and has been growing ever since. 2019 was the airport’s busiest year, with over 17 million passengers flying out of AUS. As the airport continues to recover from the impacts of the COVID-19 pandemic, the demand for air travel has significantly increased and the expected number of flights and passengers will double in 20 years. With an increasing demand for air travel and development at the airport, the airport must construct a second Jet-A fuel, or airplane fuel, facility to have enough fuel supply in the coming years to support a growing airport, a growing city and a growing economy.


New Facility Project Updates

May 2022:

Crews installed erosion control measures and began excavation for stormwater systems and electrical ductbanks. Work started on the transfer line systems and grading for an airport internal perimeter road.


Grading for new airport perimeter road


Stormwater manhole installation

April 2022:

Following the Austin City Council meeting on April 7, 2022 and vote on Item 43, the Department of Aviation issued a Notice to Proceed to the airlines to begin construction of the new fuel facility.

Construction began on the new Jet-A fuel storage facility began with the installation of temporary construction site entrances, project signage, and a project site gate. Construction crews began the installation of the Stormwater Pollution Prevention Plan and located utilities. Construction trailers and portables have been delivered to the site and will be set-up in the coming weeks for site crews and project staff to work from.

Temporary construction entrance

Temporary construction entrance


Project Background, Environmental Assessment, Community Outreach and More

Current Airplane Fuel Facility - Background & History

The airport’s main airplane fuel facility storage was constructed in 1998 and is located next to the Barbara Jordan Terminal. The current facility consists of two fuel tanks, one holds 481,000 and the other 691,700 gallons. This facility was created to be the safest and most efficient way to store and supply airplane fuel. It is continuously monitored and undergoes regular inspections by the Austin Fire Department, the Department of Aviation and the airlines. The facility is owned by the airlines that serve AUS and is operated by an independent aviation fueling services provider. The new facility will also be owned and operated by the airlines and their fueling services provider, with the same 24/7 monitoring and regular safety inspections.

For more information about the new facility, read the project fact sheet.


The Need For A New Facility 

Since the airport first opened, the number of annual passengers has tripled and the current facility no longer meets the needs of Austin’s growing community. The facility currently has a 2–3-day fuel supply, which doesn't meet the 5-7 day industry standard and cannot support future air service growth for 2022 and beyond. AUS forecasts an increase in fuel demand by an average of 3% to 5% annually over the next ten years.

The new facility will provide a more reliable, safe supply of fuel for the airlines and reliable air service for our community. It was identified as a development project through the airport’s 2040 Master Plan process. 

Watch this informational video about how AUS's fuel facility operates:


The AUS 2040 Master Plan

In 2017, the Department of Aviation began creating the 2040 Master Plan, which guides the airport’s growth as it doubles in size and serves as a roadmap to the future modernization of AUS. The need for a new fuel facility and the location of the new fuel facility were identified through this process and are in the final 2040 Master Plan document, which was approved by the Austin City Council and the Federal Aviation Administration. 

Before an airplane fuel facility is constructed, an environmental review is done to evaluate the potential environmental impact of the facility. All information from the review is presented to the Federal Aviation Administration (FAA), the administration that determines if it is safe to create a facility in the first place. If no significant impacts to air quality, socioeconomics or environmental justice, water resources, or other surroundings are expected to occur, then it’s safe to build a fuel facility. In preparation for the new fuel facility, AUS, the airlines and a team of consultants conducted an environmental review and submitted their review to the FAA. The review was granted approval by the FAA on April 8, 2020.


AUS 2040 Master Plan Public Workshops

From 2017 - 2018, the Department of Aviation hosted a series of Master Plan Public Workshops, Project Advisory Committee and Technical Advisory Committee meetings. You can review the archived meeting materials at this webpage:

  • October 12, 2017 - Public Workshop #1
  • April 19, 2018 - Public Workshop #2
  • June 7, 2018 - Public Workshop #3
  • September 6, 2018 - Public Workshop #4
Information, including project locations, for all 61 Master Plan projects were presented to the community throughout these meetings.


District 2 Fall 2021 Community Meetings

In fall 2021, the Department of Aviation and a representative from the engineering firm who is designing the new facility shared a presentation and answered community members' questions. You can view the presentation at this link.

  • October 4 - Virtual Meeting
  • November 10 - In-Person Meeting

January 29, 2022 Community Information Meetings

On Saturday, January 29, the City of Austin Department of Aviation hosted three community information meetings to inform community members and connect them to educational resources about the site selection, operations, safety, and security features of a proposed jet fuel storage facility. The meetings were in response to City of Austin Council Resolution NO. 20211209-061 and were intended to address the digital divide and language access barriers experienced by community members. One virtual meeting and two limited attendance in-person meetings were held. Both meetings provided simultaneous Spanish interpretation by professional interpreters.

View the February 7, 2022 memo from the Department of Aviation to Mayor and City Council to learn more about how these meetings were attended and publicized.

March 7, 2022 Listening Session

On March 7, 2022 Department of Aviation leadership attended a listening session led by community members to hear personal testimony for airport-adjacent neighbors and community members who were affected by the historic injustice of the East Austin petroleum storage tanks.



April 5, 2022 Austin City Council Work Session - Jet Fuel Storage Facility

AUS leadership briefed Austin City Council on the Fuel Facility Project at the City Council Work Session on April 5, 2022. The Work Session was recorded by ATXN which can be watched online at: https://austintx.new.swagit.com/videos/158053

What questions do you have about this project?

Community members are invited to share their questions ahead of the meeting. The airport team will answer as many questions as possible during the Question & Answer period of the meeting. You can also share your questions through email to AirportEngagement@AustinTexas.gov.

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
Page last updated: 22 Jun 2022, 12:36 PM