South Lamar Boulevard Corridor
South Lamar Boulevard Corridor
Project Overview
Austin Transportation and Public Works is improving safety, mobility and connectivity along South Lamar Boulevard between Barton Springs Road and U.S. 290 (Ben White Boulevard).
Funded by the 2016 Mobility Bond, the project will provide improvements for people walking, biking, driving and taking transit, while upgrading aging infrastructure along the corridor.
Final design is complete, and construction will be delivered in two segments, divided at Montclaire Street.
Southern Segment
Montclaire Street to U.S. 290
Early 2027
Anticipated construction start
Northern Segment
Barton Springs Road to Montclaire Street
2029
Anticipated construction bidding
Project Scope Update
The section of South Lamar Boulevard between Riverside Drive and Barton Springs Road, which was previously included in corridor planning, will not move forward to construction as part of this project.
Anticipated project schedules are subject to change.
Upcoming Community Event
Community Open House
South Lamar Boulevard Corridor
Date & Time
5–7 p.m.
Location
Wheatsville Co-op
Bluewillow Lounge
4001 South Lamar Boulevard
Austin, TX
Join Austin Transportation and Public Works to learn about planned improvements along South Lamar Boulevard and how construction may affect your daily travel, neighborhood or business.
At the open house, you can:
- Explore project maps and improvement plans for both construction segments.
- Learn about anticipated construction schedules and impacts.
- Speak directly with the project team.
- Share information about property access, business operations, travel needs and communication preferences.
Come when it's convenient for you!
This is a drop-in event. Stop by anytime between 5 and 7 p.m.
Planned Improvements
Both construction segments will include improvements designed to enhance safety, accessibility and mobility along South Lamar Boulevard.
Walking, biking and accessibility
- New and improved accessible sidewalks and shared-use paths
- Bike lanes
- Accessible curb ramps
- New and upgraded pedestrian crossing signals
- Improved pedestrian crossings at U.S. 290
Roadway and intersection improvements
- New and upgraded traffic signals
- New signalized intersections
- Roadway resurfacing
- Reconfigured curbs and gutters
- Raised medians at select locations
- Updated signs and pavement markings
Transit improvements
- New and relocated bus stops
- A northbound transit-priority lane between Barton Skyway and Menchaca Road
Drainage and utility improvements
- Storm drain and drainage infrastructure improvements
- Water and wastewater line upgrades
- Rain gardens
Landscaping and streetscape improvements
- New tree plantings
- Landscaping and designated planting areas
- Irrigation systems
- Other streetscape enhancements
Specific improvements vary by location along the corridor.
South Lamar corridor project map
Project Map Key
- Southern Segment · Montclaire Street to US 290
Construction anticipated early 2027
Final design is complete. The construction bid solicitation closed September 24, 2026
- Northern Segment · Barton Springs Road to Montclaire Street
Final design is complete. Permitting underway.
Construction bidding is anticipated around 2029, as the southern segment nears completion.
Mary Street Roundabout
Complete
Construction was completed in Spring 2026. Improvements also include a new shared-use path.
Del Curto / Bluebonnet Roundabout
Upcoming construction
Roundabout construction is anticipated in fall 2027 as part of the storm drain project.
What to Expect During Construction
Construction will be completed in phases to minimize disruptions along South Lamar Boulevard. However, residents, businesses and people traveling through the area should anticipate temporary changes as work progresses.
Traffic and lane closures
Temporary lane closures, traffic shifts and delays are expected. Traffic control will be phased to minimize impacts where possible.
Property and business access
Driveway access to properties along the corridor will be maintained throughout construction.
Walking and biking
Temporary sidewalk closures and pedestrian detours are expected as improvements are constructed.
Transit service
Austin Transportation and Public Works is coordinating with CapMetro on permanent and temporary bus stop relocations. Information about transit impacts will be shared as construction progresses.
Construction updates
Additional information about construction phasing, schedules, closures and detours will be provided as details become available.
Project Resources
All resource links open in a new tab.
Current Project Information
Explore capital improvement projects across Austin.
Corridor Planning and Historical Documents
The following documents were developed during earlier phases of corridor planning. Some recommendations may differ from the current construction scope.
Supporting Appendices
Stay Informed
Sign up to receive South Lamar Boulevard Corridor Project updates directly in your inbox, including construction schedules, traffic impacts and project milestones.
You can also subscribe to Austin Mobility News for weekly transportation updates from across the city.
Contact Us
Have questions about the South Lamar Boulevard Corridor Project?
Email: AustinMobilityBonds@AustinTexas.gov
Phone: 512-974-2300
Austin Transportation and Public Works
Frequently Asked Questions
Select a question below to learn more about the South Lamar Boulevard Corridor Project.
Why is the project being constructed in two segments?
The City is dividing construction at Montclaire Street to help deliver improvements more efficiently. The southern segment will be constructed first, followed by the northern segment.
Will improvements extend north of Barton Springs Road?
No. Although earlier corridor planning included the section between Riverside Drive and Barton Springs Road, that section will not move forward to construction as part of the current project.
What happened to the proposed Treadwell Street connection?
During preliminary engineering, the City requested approval from Union Pacific Railroad to connect Treadwell Street to South Lamar Boulevard through either an overpass or underpass.
Union Pacific denied both requests, and the connection was removed from the current project scope. It could be considered in the future through other mobility programs, subject to feasibility, funding and prioritization.
Is the project design complete?
Yes. Final design is complete for both construction segments. Permitting is underway for the northern segment.
Will I be able to access my home or business during construction?
Yes. Driveway access will be maintained throughout construction. Temporary lane closures, traffic shifts and pedestrian detours are expected.
How can I provide feedback?
The project team welcomes information about your access needs, business operations, travel patterns and communication preferences.
The project manager and design team will review community feedback and evaluate whether requests can be accommodated during project delivery.
How can I stay informed about construction?
Sign up for project email updates to receive information about construction schedules, traffic impacts, closures and other project milestones.
Project Timeline
April 2016
Preliminary Engineering Report
Complete
2020–2021
Preliminary design milestones
Complete
May 2026
Final design
Complete for both segments
September 2026
Southern segment bid solicitation
Complete
December 2, 2026
Community open house
Upcoming
Early 2027 • Anticipated
Southern segment construction begins
Montclaire Street to U.S. 290
Upcoming
2029 • Anticipated
Northern segment bid solicitation
Barton Springs Road to Montclaire Street
Upcoming
2030 • Tentative
Northern segment construction begins
Barton Springs Road to Montclaire Street
Upcoming
Anticipated schedules are subject to change.