South Lamar Boulevard Corridor

South Lamar Boulevard Corridor

About the Project

South Lamar Blvd Corridor

Project Overview

Status: Pre-construction

Austin Transportation and Public Works is improving safety, mobility and connectivity along South Lamar Boulevard between Barton Springs Road and U.S. 290 (Ben White Boulevard).

Funded by the 2016 Mobility Bond, the project will provide improvements for people walking, biking, driving and taking transit, while upgrading aging infrastructure along the corridor.

Final design is complete, and construction will be delivered in two segments, divided at Montclaire Street.

Southern Segment

Montclaire Street to U.S. 290

Early 2027

Anticipated construction start

Northern Segment

Barton Springs Road to Montclaire Street

2029

Anticipated construction bidding

Project Scope Update

The section of South Lamar Boulevard between Riverside Drive and Barton Springs Road, which was previously included in corridor planning, will not move forward to construction as part of this project.

Anticipated project schedules are subject to change.

Upcoming Community Event

Community Open House

South Lamar Boulevard Corridor

Date & Time


5–7 p.m.

Location

Wheatsville Co-op
Bluewillow Lounge
4001 South Lamar Boulevard
Austin, TX

Join Austin Transportation and Public Works to learn about planned improvements along South Lamar Boulevard and how construction may affect your daily travel, neighborhood or business.

At the open house, you can:

  • Explore project maps and improvement plans for both construction segments.
  • Learn about anticipated construction schedules and impacts.
  • Speak directly with the project team.
  • Share information about property access, business operations, travel needs and communication preferences.

Come when it's convenient for you!

This is a drop-in event. Stop by anytime between 5 and 7 p.m.

Planned Improvements

Both construction segments will include improvements designed to enhance safety, accessibility and mobility along South Lamar Boulevard.

Walking, biking and accessibility

  • New and improved accessible sidewalks and shared-use paths
  • Bike lanes
  • Accessible curb ramps
  • New and upgraded pedestrian crossing signals
  • Improved pedestrian crossings at U.S. 290

Roadway and intersection improvements

  • New and upgraded traffic signals
  • New signalized intersections
  • Roadway resurfacing
  • Reconfigured curbs and gutters
  • Raised medians at select locations
  • Updated signs and pavement markings

Transit improvements

  • New and relocated bus stops
  • A northbound transit-priority lane between Barton Skyway and Menchaca Road

Drainage and utility improvements

  • Storm drain and drainage infrastructure improvements
  • Water and wastewater line upgrades
  • Rain gardens

Landscaping and streetscape improvements

  • New tree plantings
  • Landscaping and designated planting areas
  • Irrigation systems
  • Other streetscape enhancements

Specific improvements vary by location along the corridor.

Map of the South Lamar Boulevard Corridor Project showing the southern construction segment from U.S. 290 to Montclaire Street, the northern segment from Montclaire Street to Barton Springs Road, and the locations of the Mary Street and Del Curto Road/Bluebonnet Lane roundabouts.

South Lamar corridor project map

Project Map Key

  • Southern Segment · Montclaire Street to US 290

    Construction anticipated early 2027

    Final design is complete. The construction bid solicitation closed September 24, 2026

  • Northern Segment · Barton Springs Road to Montclaire Street

    Final design is complete. Permitting underway.

    Construction bidding is anticipated around 2029, as the southern segment nears completion.

  • Mary Street Roundabout

    Complete

    Construction was completed in Spring 2026. Improvements also include a new shared-use path.

    See photos of the completed roundabout.

  • Del Curto / Bluebonnet Roundabout

    Upcoming construction

    Roundabout construction is anticipated in fall 2027 as part of the storm drain project.

What to Expect During Construction

Construction will be completed in phases to minimize disruptions along South Lamar Boulevard. However, residents, businesses and people traveling through the area should anticipate temporary changes as work progresses.

Traffic and lane closures

Temporary lane closures, traffic shifts and delays are expected. Traffic control will be phased to minimize impacts where possible.

Property and business access

Driveway access to properties along the corridor will be maintained throughout construction.

Walking and biking

Temporary sidewalk closures and pedestrian detours are expected as improvements are constructed.

Transit service

Austin Transportation and Public Works is coordinating with CapMetro on permanent and temporary bus stop relocations. Information about transit impacts will be shared as construction progresses.

Construction updates

Additional information about construction phasing, schedules, closures and detours will be provided as details become available.

Project Resources

All resource links open in a new tab.

Current Project Information

Austin Capital Projects Explorer

Explore capital improvement projects across Austin.

Stay Informed

Sign up to receive South Lamar Boulevard Corridor Project updates directly in your inbox, including construction schedules, traffic impacts and project milestones.

You can also subscribe to Austin Mobility News for weekly transportation updates from across the city.

Contact Us

Have questions about the South Lamar Boulevard Corridor Project?

Email: AustinMobilityBonds@AustinTexas.gov

Phone: 512-974-2300

Austin Transportation and Public Works

Frequently Asked Questions

Select a question below to learn more about the South Lamar Boulevard Corridor Project.

Why is the project being constructed in two segments?

The City is dividing construction at Montclaire Street to help deliver improvements more efficiently. The southern segment will be constructed first, followed by the northern segment.

Will improvements extend north of Barton Springs Road?

No. Although earlier corridor planning included the section between Riverside Drive and Barton Springs Road, that section will not move forward to construction as part of the current project.

What happened to the proposed Treadwell Street connection?

During preliminary engineering, the City requested approval from Union Pacific Railroad to connect Treadwell Street to South Lamar Boulevard through either an overpass or underpass.

Union Pacific denied both requests, and the connection was removed from the current project scope. It could be considered in the future through other mobility programs, subject to feasibility, funding and prioritization.

Is the project design complete?

Yes. Final design is complete for both construction segments. Permitting is underway for the northern segment.

Will I be able to access my home or business during construction?

Yes. Driveway access will be maintained throughout construction. Temporary lane closures, traffic shifts and pedestrian detours are expected.

How can I provide feedback?

The project team welcomes information about your access needs, business operations, travel patterns and communication preferences.

The project manager and design team will review community feedback and evaluate whether requests can be accommodated during project delivery.

How can I stay informed about construction?

Sign up for project email updates to receive information about construction schedules, traffic impacts, closures and other project milestones.

Project Timeline

April 2016

Preliminary Engineering Report

Complete

2020–2021

Preliminary design milestones

Complete

May 2026

Final design

Complete for both segments

September 2026

Southern segment bid solicitation

Complete

December 2, 2026

Community open house

Upcoming

Early 2027 • Anticipated

Southern segment construction begins

Montclaire Street to U.S. 290

Upcoming

2029 • Anticipated

Northern segment bid solicitation

Barton Springs Road to Montclaire Street

Upcoming

2030 • Tentative

Northern segment construction begins

Barton Springs Road to Montclaire Street

Upcoming

Complete
Upcoming

Anticipated schedules are subject to change.